Engineering inputs
Set the engineering assumptions and design parameters.
Equipment and power inputs
Engineering results
Review calculated capacity, limits and design checks.
RACK CAPACITY TOOL
Estimate power, heat, cooling and operating cost for network racks, edge rooms and small data centers.
Set the engineering assumptions and design parameters.
Review calculated capacity, limits and design checks.
Use this calculator for a network switch rack, edge computing cabinet, telecom room or small data center. It separates connected equipment power, estimated operating load and design allowances so that early power and cooling conversations use the same assumptions.
Connected load is device watts multiplied by quantity. Actual IT load applies utilization; design power then applies growth and redundancy as two successive allowances. Apparent power is design watts divided by power factor.
The redundancy field is a planning allowance only. It does not prove N+1, 2N or A/B-path resilience.
Single-phase current uses I = VA ÷ V. Three-phase current uses I = VA ÷ (√3 × V), assuming a balanced load and that the entered voltage is line-to-line. The status badge uses 80% of the entered breaker or PDU rating as a planning threshold, not as a universal code rule.
The heat estimate uses design power and 1 W ≈ 3.412 BTU/h; refrigeration tons use 12,000 BTU/h per RT. Cooling input is simplified as design watts divided by COP, where COP is cooling effect divided by input work. Room airflow, inlet conditions, humidity, hot spots and equipment density still require site-specific thermal design.
Daily and monthly energy use the actual IT load, operating hours and days. They exclude cooling electricity, UPS or PDU losses, lighting and other facility overhead. For a facility-wide estimate, account for those loads separately; PUE compares total facility energy with IT equipment energy.
Use nameplate or connected power to understand the upper bound, then use representative measured or vendor peak demand for utilization. Confirm the final circuit, UPS and PDU design against equipment specifications and site measurements.
No. Design power is the estimated IT load after growth and redundancy allowances. The cooling-input result is a separate simplified estimate, while monthly energy and cost on this page cover the actual IT load only.
Single-phase current is calculated as apparent power divided by voltage. Three-phase current divides by the square root of three and assumes a balanced load with line-to-line voltage entered.
No. It is only a multiplicative planning allowance. It does not model UPS topology, dual-cord distribution, component failure, transfer paths or verified failover capacity.
No. It is a conservative planning threshold used by this calculator. Final designs must follow local electrical rules, continuous-load requirements, equipment ratings, connector limits, derating and phase-balance checks.
Use the result for early planning and comparison. A qualified electrical or mechanical professional should verify protection, conductor sizing, UPS/PDU topology, airflow and cooling capacity before deployment.
ENGINEERING WORKFLOW
Verify PoE source capacity, cable voltage delivery, rack power and cooling, then estimate telecom battery backup runtime.